Non-Process Infrastructure
Package Number | Description | Estimated Pre-Qualification Start | Estimated RFP Issue | Estimated Award |
CG2804 | Pre-Engineered & Modular Buildings - Package 1 | December 2022 | January 2024 | October 2024 |
CG2805 | Pre-Engineered & Modular Buildings - Package 2 |
December 2022 | June 2024 | May 2025 |
CG2804 – Pre-Engineered & Modular Buildings – Package 1
The scope of work for package CG2804 – Package 1 (NPI buildings), includes the supply (fabrication and delivery to site), installation, construction and commissioning the entire building and building systems listed below:
- Emergency Response and Mine Rescue Facility (repurposed freeze plant)
- Admin, Mine & Mill dry building (new building)
- Heated Warehouse (new building)
- External Works.
CG2805 – Pre-Engineered & Modular Buildings – Package 2
The scope of work for package CG2805 – Package 2 (NPI buildings), includes the supply (fabrication and delivery to site), installation, construction and commissioning the entire building and building systems listed below:
Maintenance & Workshop, Heavy/Light Vehicle Maintenance, Mill Support, Laboratory, Rail Support Facility, Enclosed Walkway and External Works.
Mining
Package Number | Description | Estimated Pre-Qualification Start | Estimated RFP Issue | Estimated Award |
CG1102 | Mining UG Construction SMPEI |
June 2022 | May 2023 | September 2024 |
CG1102 – Mining UG Construction SMPEI
This package is to support mining ramp up, installation of permanent mine infrastructure and equipment with staged commissioning, and handover to BHP Operations. The scope includes the execution of the structural, mechanical, piping, electrical and instrumentation (SMPEI) works critical to first production.
The Scope of Work also includes:
- Raw Ore and Surge bins (including bin excavation).
- Permanent Bulk Material Handling (BMH) conveyors.
- Facilities
- Underground electrical substation.
*The timelines provided are estimates and may be subject to change